Project Road
Overview
- A total of 19,700 SqMt of road to be relaid.[RoadLaying.doc]
- main road to Park - 1575
- 1st Main - 350 sqmt
- 12th 1st cross - 675 sqmt
- remaining - 17000 Sqmt
- 1600 SqMT of Wet Mix for badly damaged roads.
- 25- 40-50mm planned.
Objectives
- Ensure ALL roads of LW be of the same standard.
Team
- Abdur Basheer Project Manager
- Naveen C
- Tejasvi B.K
Timeline
- Quotes: October 2009 [Roadquotes.doc] [ all 3 quotes in one file]
- 165 SqMT - Govindaraju.
- 285 SqMt - Akar Associates
- 180 SqMT- SSA - Lokesh R
- Fund proposal: October 2009 - Shuba / Dhaval [ Maintfee_Road improvment_proposal.pdf ]
- Seek Approval: Presented plan and obtained approval from the GB. [EGM_Minutes_13_Dec09.pdf ]
- Implement : Jan 2010 Feb 2010
- Complete: Feb-Mar Jul 2010
Vendor
| Vendor GovindaRaju LW_RoadWO_Ltrhd_v3.doc [work order] |
| Total Area |
19700 Sqmt |
| Cost |
33L 36L [ an increase of Rs15 per Sqmt from the time we obtained the quote ] |
| Consultant |
50K |
| Terms |
Pay 15L after 90% of work is completed. [ 5L for every 30% ]
Remaining amount to be paid within 12 months .
Consultant approves the work and payment to the contractor |
Consultant
| Civil Aid Techno Clinic (P) LTd. www.civilaid.com |
1. Civil aid propose to take one core sample for every 1000 sq. metre. 2. Minimum of 6 cores shall be offered for extraction after the completion of the road work. 3. Core extraction charges are Rs. 1000 per sample 3. Following are the tests to be conducted on extracted core samples. Thickness .... Rs. 200/- per sample Bitumen Content.... Rs. 700/- per sample per layer Gradation of aggregates Rs. 300/- per sample per layer Density Rs. 200/- 4. Transportation charges of Rs.1500/- per day and generator charges Rs. 500/- will be charged extra. |
Supervisors
3 engineers will be deputed . 2 onsite when the Wetmix/ asphlating is going on and 1 at the plant to supervise the quality of the mix etc.
They have proposed to conduct
- Depth checking . Temperature checking.
- Camber and profile correction and Pre measurment.
- Bitumen check and setting at the plant
Tasks/Milestones
- Apply Seal Coat [ which is 105 Rs SqMT extra ] around the park area. This provides a smooth coat for members to walk / bike / kids to play.
- Identify the different 1600 SqMT which requires WetMix [ badly damaged road]
| Tasks |
Lead |
Notes |
Start Date |
End Date |
Status |
| Obtain quotes |
Basheer
Naveen
|
Akar Associates
GovindaRaju
SSA - Lokesh R
|
Oct -09 |
Oct-09 |
DONE |
| Fund Proposal |
Dhaval
Shuba
|
Member friendly
Payment Schedule
|
Nov-09 |
Nov-09
|
DONE |
| |
|
|
|
|
|
| Finalize Vendor |
Basheer
Naveen
Tejasvi
|
One vendor based
On quality and Price
Payment Schedule Friendly
|
Dec-09 |
Dec-09
Jan-10
|
DONE |
| Send Notice |
Tejasvi |
Notice to construction Owners to
begin road cutting before the work
starts
|
Jan-10 |
Feb-10 |
DONE |
| Consultant |
Basheer
Naveen
|
seek professional help to test quality of work. |
Jan-10 |
Jan-10
Feb-10
|
DONE |
| Implement |
Basheer
Naveen
Tejasvi
|
work to completed in 3 stages.
Consultant approves the work and
Payment.
| Work |
Payment |
|
| 30% |
6.5L |
6.5 |
| 30% |
6.5L |
13 |
| 40% |
6.5L |
19.5 |
| |
Remaining tobe Paid in 12 months |
|
|
Jan-10 |
Jan-10
Jul -10
|
DONE |
| Complete |
|
Delays;
1. After initial phase - Naveen on Vacation
2.Basheer on vacation.
3.Rains delayed.
4. 2nd main dug up for Sewage line reinforcement.
5.Travel due to work assignments
|
Mar-10 |
Mar10
May 30
Jul 10
|
Done |
| Repair work |
|
|
|
|
WIP |
Risks
- Any vendor can stop the work half way through.
- Pay in stages after the roads are laid.
- Hold 7-8L for a year
- low lying areas , ones with lot of trees get damaged
- Water flowing from every house will damage the roads.
- New construction issues
Payment Tracker
All Payments and Measurement[estimate and actual] details in a separate window here
Residents Contribution
Details of advance payment made by the residents here
FAQ
Road Cutting by plot owners - what do we do ?
- LWORA will work on the option of empanelling two contractors for regular construction activities within the estate.
- If a plot owner requires road cutting, the subsequent patch up will be undertaken by the empanelled contractors
- The empanelled contractors will ensure that the patch up is undertaken to the specifications agreed by LWORA
- The charges for the patch up will be standardized
- The charges will be invoiced to the Plot owner